Commissioners approve data center ordinance
The Whitehall Township Board of Commissioners officially approved an ordinance regarding data centers and how the township will amend the zoning code to include terms and criteria for the hyperscale centers.
The data center ordinance passed unanimously 7-0 at the Nov. 9 meeting. In August, the board held a first hearing regarding this ordinance and entertained public comment regarding fears and anxiety about data centers.
After the ordinance was up for a first hearing, it was sent to the township planning commission and the Lehigh Valley Planning Commission for review, and according to Commissioner Taylor Stakes, both groups recommended approval.
Stakes thanked Bureau Chief Lee Rackus for developing the ordinance for the township, along with township Solicitor Jack Gross.
Stakes said the ordinance will provide protection for the township, along with regulations and protections for citizens.
“This is a moving target,” Stakes said. “We will most likely have to update this at some point in the future as things change. I think this is a strong ordinance to protect our township from the harms of data centers.“
Many residents spoke against the idea of data centers at the first hearing during the summer, particularly whether a data center could be built in this township or nearby. Each resident expressed their fears, concerns and anxiety about the idea of a data center entering the area.
According to the supporting documents, the zoning ordinance added many terms regarding data centers such as artificial intelligence, cryptocurrency mining, data center, data center accessory use, hyperscale data center and other definitions.
The supporting documents highlight three rules and requirements for applicants regarding data centers within the zoning ordinance.
• “No data center uses shall be located on prime agricultural soils.”
• “All data center uses shall be designed and/or arranged to avoid detrimental impacts to high value streams, wetlands, floodplains, steep slopes or other environmentally sensitive areas.”
• “All data center uses shall be designed and arranged so as to minimize disturbances to natural and unimproved land and shall encourage the preservation of mature trees and woodland areas.”
The ordinance passed by the board included rules and requirements that developers must obey and meet for a project like this, including water requirements, sound studies and more.
After hearing from the public and getting an official recommendation from both the township and Lehigh Valley planning commissions, the commissioners voted to pass the data center ordinance, which can be amended again in the future.