Road Work
City officials report a number of upcoming road projects.
S. New Street
• Ongoing – to be competed on Monday 7/7 or Tuesday 7/8
• Closed between Third Street and Mechanic Street, local access only between Mechanic Street and Fourth Street
o NOTE: You can still access the parking garage on New Street during this time, please speak with the flaggers at New and Fourth and they will let you in
• Detour: Fourth Street -> Brodhead Avenue -> Third Street
E. 3rd Street
• Ongoing – to be completed by Tuesday 7/15
• Westbound lane and all parking closed between Webster and New Street
o NOTE: Busses and Emergency vehicles can pass through if they indicate/speak with the flaggers
• Detour: Webster Street -> Columbia Street -> Second Street -> Northampton Street
Summit Street
• Ongoing – to be completed around 8/2
• Closed from Brodhead Ave to Wyandotte Street
o They close a section of the road down each day, with a shifting detour
• Detour: Wyandotte Street -> Fourth Street -> Brodhead Avenue
E. Washington Avenue
• Ongoing – to be completed around 8/15
• Closed from Minsi Trial Street to Stefko Boulevard
• Detour: Minsi Trail Street -> Pembroke Road
Center Street
and North Street
• Tuesday 7/8 – TBD (roughly 1 month)
• Right lane of Center Street and all of North Street between Center Street and Pine Street closed
o Parking Lot at Center and North Street will retain access via North entrance
• Detour: Union Boulevard -> High Street
E. 4th Street
• Tentative 7/9 – TBD
• 4th Street closed from New Street to Adams Street
• Detour: New Street -> Morton Street -> Adams Street
Vine Street
and Packer Avenue
• Friday 7/11 – TBD (roughly 1 month)
• Vine Street closed from Morton Street to West Packer Avenue, later W Packer Ave closed from Brodhead to Vine Street
o Access will remain for school traffic if this closure runs past schedule
Vine Street
and W Graham Place
• Friday 7/11 – TBD (roughly 1 month)
• 1 block closures on Vine Street from Morton Street to W Graham Place, then W Graham Place closed
o Flaggers will assist with access to Rink Street heading the wrong direction when relevant
o Exit from Parking Garage will remain open
Columbia Street
and Adams Street
• Wednesday 7/16 – TBD
• Traffic plan TBD
o Columbia Street from Webster Street to Adams Street
o Adams Street from Columbia Street to Third Street